As the
population in the Front Range of Colorado continues to grow, it is becoming
increasingly necessary to find ways to accommodate the needs of this population
while minimizing or mitigating harm to the indigenous natural resources and
protecting the little wildlife habitat that remains. Aquatic and Wetland
Company (AWC), an ecologically-based design/build company based in Ft. Lupton,
Colorado recently completed a stream restoration project that illustrates how it
is possible to meet these two needs in a single project. The project,
completed this past August, involved a 3,600 foot reach of Sand Creek near the
old Stapleton Airport.
![]() |
![]() |
Bluff Lake Park is a 123-acre parcel that includes a lake, 30 acres of wetland areas, a 0.7 mile stretch of the Sand Creek corridor, short grass prairie and a remnant cottonwood gallery. The reach of Sand Creek that extends through the park near the old Stapleton Airport in Denver, Colorado presented particularly challenging erosion control issues. The soils along the entire corridor are highly erodible sands. Runoff to the stream has increased dramatically in recent years due to increased development throughout the watershed. The flows that Sand Creek must convey are extremely flashy and markedly higher than natural levels. The streambanks have to accommodate this overload. These flow conditions had created vertical banks that were over 12’ high in some areas as well as channel downcut to 4’. Both these factors contributed to the degradation, and in many areas, lack of riparian habitat. In addition to the high flows and erodible material, the project presented other challenges, including existing structures in need of protection. The option of energy dissipation through floodplain widening was not economically or politically feasible. Therefore, the project design/build team developed several erosion control techniques to address the issues at hand.
The goals of the project were to stabilize the highly erodible banks, lessen the channel gradient to a slope deemed stable for sand systems, restore riparian and upland vegetation along the creek corridor, augment wetland habitat, and maintain compatibility with the adjacent environmental education facility. Because of the combination of a high need for stability and the goal to restore biological functioning to the corridor, the design plan needed to creatively integrate stabilization techniques known to be effective for these different challenges. To meet these goals, Aquatic and Wetland Company took a design approach that embodied three main principles: integrate hard protection and soft, bioengineered treatments, restore biological function and create a meandering low flow channel within an armored flood channel.
Immediately after construction |
Second growing season |
AWC used
several bioengineering techniques on the project. A double terrace with
boulder toe and brush layering were used to treat the high, eroded banks
throughout most of the project. This treatment consists of a row of
boulders placed on a rubble foundation at the toe and the top of the
slope. Between the boulder toes, the bank is graded to a 3:1 slope to
create a planting terrace. Brush layering is installed at an angle behind
the lower row of boulders. Biodegradable erosion control fabric was placed
on the terraces to provide initial stabilization until the plants form a root
structure. The slope protection in this treatment comes primarily from the
two rows of boulders and secondarily from the root structure, which will be
created as the vegetation matures. The vegetation also serves to create
riparian habitat and function. Amendments added with the plantings
included slow release fertilizer, mycorrhizal inoculants and polymer. The
brush layering will eventually grow out over the boulders, screening them from
view to create a more natural look. Additionally, the brush layering
provides shade and overhead cover for fish. By the end of the first
growing season, some of the brush layering had grown almost 4
feet.
![]() |
![]() |
![]() |
![]() |
In some areas, specifically low-risk inside bends, hard treatment was not necessary. In these areas a willow log designed specifically for the project was used for toe material. The logs were constructed by hand onsite using available fill material from the project site with some imported mulch to supplement onsite material. To construct the willow logs, a rectangular piece of erosion control fabric was laid out flat. A strip of mulch and native soil mixed with fertilizer and moisture holding polymer was spread along one long side. A wide strip of willow cuttings was laid out along the other long side. Beginning with the mulch side, the fabric was rolled up burrito-style with the willows ending up on the outermost layer. The log was then staked into place at the toe of the slope. Willow wattling was installed behind the log. The intent of the specialized willow logs was to have the outer willow layer in the log producing stabilizing roots and overhead foliage which was augmented by the willow wattles to double the effect. Several months after installation, the treatment showed exceptional growth and resistance to high flow events.
Aquatic and Wetland Company secured the necessary 404 permits for the project. Mitigation required under the permit the creation of 0.14 acres of wetland habitat to compensate for impacts incurred during construction. The wetland area is designed to accommodate effluent from the Aurora Wastewater Treatment plant but will not be dependent on the plant. The wetland is sustained hydrologically by flows in Sand Creek. Willow logs were used again to create a check structure for the inflow of effluent.
All of the vegetation, including seed mixes and potted transplants that were grown at the AWC nursery facility, were comprised of species indigenous to the Sand Creek corridor. The species were selected and laid out to replicate the communities found in undisturbed riparian corridors in the Colorado Front Range. These included cottonwood galleries, riparian scrub/shrub and transitional shrub zones, wetland zones, riparian perennial zones and shortgrass prairie zones. The planting plan showed sensitivity to the project’s location within an environmental education facility. The diversity of habitat has already proven to be attractive to a variety of wildlife. Great blue heron and black crowned night heron have been seen hunting along the creek and in the new wetland area. A duck family has been routinely observed near the new wetland. Other wildlife at the park include fox, coyote, Swainson’s hawk and great horned owl.
The project is
a good example of the integration of hard and soft erosion control techniques
and the necessity for both. Combined with the sound application of engineering
principals, bioengineering can be an appropriate solution for managing erosive
floodwaters. The reach of Sand Creek that runs through Bluff Lake
Environmental Education Center will mature to fulfill its obligation as an
educational resource that provides functional wildlife habitat while reducing
threats to existing structures and adjacent property.
Home Consulting Group Construction Group Native Plant Nursery
Interesting
Projects Plant Inventory
List Regulatory
Information
Aquatic and Wetland Company
9999 Weld County Road 25, Ft.
Lupton, CO 80621, 303.442.4766, 303.857.2455 fax
brad@aquaticandwetland.com